How is Porthos progressing now?
Implementation works for Porthos have started from spring 2024. The overview below gives an overall schedule of the work:
January 2024 | Start of construction |
First half 2024 – early 2026 | Onshore pipeline |
First half 2024 – mid 2026 | Compressor station |
First half 2024 – early 2025 | Cooling water intake building |
First half 2025 – end 2025 | Platform |
First half 2025 – end 2025 | Wells |
Mid 2025 – end 2025 | Offshore pipeline |
2026 | Porthos system operational |