How is Porthos progressing now?

Implementation works for Porthos have started from spring 2024. The overview below gives an overall schedule of the work:

 

January 2024 Start of construction
First half 2024 – early 2026 Onshore pipeline
First half 2024 – mid 2026 Compressor station
First half 2024 – early 2025 Cooling water intake building
First half 2025 – end 2025 Platform
First half 2025 – end 2025 Wells
Mid 2025 – end 2025 Offshore pipeline
2026 Porthos system operational